Kaiāulu O Lānaʻi Housing Town Hall

With clearing underway for Kaiāulu O Lānaʻi, the planned 72-unit affordable housing development beyond the end of Fifth Street, residents met with the construction team November 17 at ILWU Hall to discuss construction plans, traffic and safety.

Councilmember Gabe Johnson organized the town hall in response to community construction concerns. Representatives from Maryl Construction, Goodfellow Brothers and the Maui County Department of Housing attended to answer questions about access, scheduling and the workforce.

Fifth Street construction traffic was a focus, particularly where children travel between the school, youth center, skate park and basketball/tennis courts. Construction representatives said they had coordinated with school principals and the youth center to keep deliveries and large-truck movements outside school arrival and dismissal times.

Residents asked that planning also account for children crossing throughout the day and park activity continuing into the evening. An alternate construction entrance was requested.

Fifth Street is currently the project’s only available access. Representatives said discussions with Pūlama Lānaʻi about another route were underway. Access, fees and road maintenance would need to be addressed before private roads could be used.

Clearing and grubbing at the site were expected to continue until approximately December 14. Work includes tree and debris removal and a 12-foot-high fence separating construction activity from neighboring homes.

Building construction was projected to begin around April or May 2027, subject to permits, and take approximately two years. Plans include 46 single-family homes and 26 units in the kūpuna housing component, plus a community center and park space.

The workforce could reach 100 to 150 field workers during peak construction. Residents asked about local hiring and guidance for incoming workers on community rules and speed limits. Representatives said hiring would depend on the contractors and subcontractors involved.

Questions about applications, eligibility and home layouts also came up. A separate meeting was planned for December to address the housing process.

Below is a pictured link to the Kaiāulu O Lānaʻi information packet which details site plans, home designs, proposed rents and income level requirements.




Next
Next

A Seed Bank for Lānaʻi: Kuahiwi a Kai’s Restoration Work Continues